Beach house progress:

  • Demolition and re-grading completed in early June
  • Deep underground utilities and vault install completed by end of June
  • Footings and stem walls completed by mid-July
  • Plumbing and electrical below slab completed early August

Next Steps:

  • Pour foundation
  • Finish underground utilities
  • Pour sidewalks
  • Paving


The diagram above details the Incline Beach House construction zone and modified Incline Beach parking areas.

Click here for what to expect during 2026 beach season

Where is the project at in the planning/design/construction process?

Feb. 26, 2026 Update: The Project Construction Manager (Core Construction) completed the required competitive bidding process for the project in October 2025. Following receipt of the subcontractor bids, the Guaranteed Maximum Price (GMP) was negotiated with IVGID Project Management Staff, and the final construction contract was approved by the Board of Trustees on December 10, 2025. Refer to the Board-related information documents below for additional details.

Final project permitting is currently in process with Washoe County and the Tahoe Regional Planning Agency (TRPA).

Exhibits showing the planned construction zones and areas of Incline Beach that will remain open for public use and parking during construction and a final layout are available via the links below.

EXHIBIT: PUBLIC/PARKING ACCESS DURING CONSTRUCTION Link

BOARD-RELATED INFORMATION Link to Board Meeting 12/10 Memo Item H.1.

What is the Incline Beach House Project?

The Incline Beach House Project has a history dating back to 2016 and has undergone multiple planning iterations since its inception. As one of the largest capital improvement projects at the Incline Village beaches in many years, the Incline Beach House Project (project # 3973LI1302) will involve the tear down and rebuilding of the Incline Beach restrooms and food service building.

 

Incline Beach House site logistics

Renderings (Click to enlarge)

beach house renerings

stage view of Incline beach house

Oct. 7, 2025 update: IVGID’s Engineering Team opened bidding for the construction phase of the project on October 2, with bidding closing on October 23. The hope is to choose a construction firm and get through the Guaranteed Maximum Price (GMP) negotiations in time to return to the Board of Trustees with a GMP for the project as currently scoped on December 10, 2025.

Permits for the project were submitted to the TRPA on September 19. At the IVGID Board of Trustee’s September 17 meeting, the Trustees reaffirmed their support for a select list of added alternates to the project. Please view the linked documents below for details on planned construction areas, areas of Incline Beach which will be open for public use and parking during the construction, and the locations of the added alternates.

June 24, 2025 update:  The Design-Build Team at CORE Construction has submitted Design Development Drawings (linked below) and will now proceed with Construction Drawings, which are scheduled for submission at the end of August.

On January 29, 2025: IVGID’s Public Works staff presented a comprehensive overview of the history of the Incline Beach House Project to the IVGID Board of Trustees. Click here to download the memo (PDF).

In January 2022: The IVGID Board of Trustees identified the Incline Beach House Project in the Community Services Master Plan as a “priority project” and “top tier recommendation.”