Community Services Master Plan   |   District Strategic Plan   |   Diamond Peak Master Plan

Project Updates

WRRF Aeration System Improvements

 

This project funds the design and replacement of the aeration system equipment at the WRRF. The Board awarded the construction contract to KG Walters on December 11, 2019. The Contractor has mobilized to the site and begun construction. An overhead access door has been installed on the aeration building to facilitate replacement of the blowers. Construction will continue until December 2020. IVGID has been put on notice that there may be COVID-19 delays but so far the Contractor and their material suppliers are continuing to work, since they are considered essential businesses.

 

K. G. Walters Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$1,508,500

$384

$1,508,884

$151,894

$1,357,080

 

Water Reservoir Safety and Security Improvements – Phase 1

 

This project will replace the ladders that access the top of the water reservoirs, install intermediate access platforms, install protective railings and install new fall protection devices for District staff safety, and to meet current OSHA safety standards. The Board awarded the contract to Resource Development Company on April 10, 2019. The Contractor has submitted shop drawings for the proposed modification and is anticipated to mobilize to the site in early June. Construction is expected to be substantially complete by September 15, 2020.

 

Resource Development Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$362,600

$0

$362,600

$0

$362,600

 

Mountain Course Clubhouse Renovation

 

This project renovated the Mountain Golf Course clubhouse after a fire in the kitchen forced the District to close the facility for repairs.  The remodel includes a larger deck and ADA access. Work is substantially complete and the contractor, Houston Smith Construction, is progressing through the few remaining punchlist items.

 

Houston-Smith Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$1,006,000

$87,893

$1,093,893

$1,072,015

$21,878

 

IVGID Recreation Center Site Lighting Replacement

 

A 2020 Capital Improvement Project to replace bollard and site lights with modern LED fixtures. An outside Electrical Engineering firm has completed design and the project has been awarded to Intermountain Electric, Inc. Construction started on June 1st and is scheduled to be substantially complete on or before June 26th.

 

Intermountain Electric Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$84,856

$0

$84,856

$0

$84,856

 

Incline Village Bocce Courts

 

At the August 14, 2019 Board of Trustees meeting, the Board prioritized construction of bocce courts. Engineering staff has completed design and at the May 6th Board of Trustee meeting, the Board approved the Notice to Proceed. Rapid Construction will begin construction the week of June 8th and be substantially complete on or before July 24th.

 

RaPiD Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$68,860

$0

$68,860

$0

$68,860

 

2020 Watermain Replacement & Fire Flow Enhancement Project

 

Nine responsive and responsible bids were

publicly opened on May 28, with contractors

“social distancing” in the Public Works front

parking lot to hear the results (photo). Bids

were very competitive (two of them were only

$2 apart). Apparent low bidder is RaPiD

Construction, who is also the contractor on

the Bocce Court project and the Incline Park

Facility Improvements (ballfield) project. A

recommendation to award the work is

anticipated to go to the Board on June 24.

 

Tennis Center Renovation

 

Six responsive and responsible bids were publicly opened on May 21, with the apparent low bidder being Daniel Fraiman Construction of Truckee. A recommendation to award this project is anticipated to go to the Board on June 10. If awarded, construction is scheduled to begin mid-August and is expected to be substantially complete by April 1, 2020.

 

Championship Course Maintenance Building Drainage & Washpad Improvements

 

This project is currently out to bid; bid opening is scheduled for June 11thBid results will be presented at the June 24th Board of Trustees meeting.

 

The Engineering Division is also overseeing a number of projects in the construction, bidding, design and planning phases, including (but not limited to): District pavement maintenance and maintenance and upgrade projects at the WRRF and BCWDP.

 

Contract administration and administrative support for the month included those projects listed in the various division reports included herein, and support for other capital improvement projects underway throughout the District, including upgrades to Diamond Peak’s Lodgepole lift electrical panels, where bids were opened publicly on May 28.

District Contact: Nathan Chorey 775-832-1372

For information on current NDOT projects:
www.nevadadot.com/projects
 

For information on current Washoe County projects:
http://www.washoecounty.us/csd/engineering_capitalprojects/index.php