WRRF Aeration System Improvements

 

The aeration process of wastewater treatment supplies oxygen to facilitate the biological activity that converts raw sewage into treated wastewater effluent. The plant has six-200,000-gallon aeration basins with two jet aeration clusters per basin supplied by computer controlled multistage centrifugal aeration blowers. This project funds the design and replacement of the aeration system equipment at the WRRF. The Board awarded the construction contract to the lowest responsive bidder, KG Walters, on December 11, 2019. Construction has commenced and is anticipated to continue until December 2020. Progress meetings are held every two weeks.

 

K. G. Walters Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$1,508,500

$6,069

$1,514,569

$210,704

$1,303,864

 

Water Reservoir Safety and Security Improvements – Phase 1

 

This project will replace the ladders that access the top of the water reservoirs, install intermediate access platforms, install protective railings and install new fall protection devices. The exterior access to the roof area is required to meet the needs of the District to monitor the water quality in the reservoirs and perform routine repairs to radio communication equipment. The ladders also need to be secured from access by the public. The reservoir ladders, fall protection, platforms, and protective railings will meet the current Occupational Safety and Health Administration (OSHA) safety standards. The Board awarded the contract to Resource Development Company on April 10, 2019 for 10 of 13 reservoirs. Construction begins this summer and is expected to be substantially complete by September 15, 2020.

 

Resource Development Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$362,600

$0

$362,600

$0

$362,600

 

Water Reservoir Safety and Security Improvements – Phase 2

 

The second phase of this project will also replace the ladders that access the top of the water reservoirs, install intermediate access platforms, install protective railings and install new fall protection devices for the remaining 3 reservoirs. The construction contract was awarded at the June 10, 2020 Board of Trustees meeting. Construction is scheduled to begin this summer and is to be completed by the end of the year.

 

Paso Robles Tank, Inc Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$109,000

$0

$109,000

$0

$109,000

 

2020 Watermain Replacement & Fire Flow Enhancement Project, Martis Peak Road

 

imageA 2020 Capital Improvement Project, this project includes slip lining a 14-inch water main under State Route 28 and replacing aging steel water main in Martis Peak Road and Rifle Peak Court. Three new fire hydrants will be installed in the area, as well (photo).  IVGID Engineering Staff completed the design, and the construction contract was awarded at the June 23, 2020 Board of Trustees meeting. Construction has begun, residents have been notified, and the project is scheduled to be completed by the end of September.

 

RaPiD Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$456,610

$0

$456,610

$0

$456,610

 

Incline Village Bocce Courts

 

Work is complete on the four new bocce courts, scoreboards have been installed, and a spigot for water was installed at the site at the request of the Parks Department.

   

RaPiD Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$68,860

$1,200

$70,060

$70,060

$0

 

Tennis Center Renovation

 

The project includes remodeling the pro-shop and restrooms, enclosing the existing kitchenette area, expanding and enhancing the deck area, and layout improvements to make the venue more welcoming. The construction contract was awarded at the June 10, 2020 Board of Trustees meeting. Construction is scheduled to begin August 17th and is expected to be substantially complete by April 1, 2021.

Daniel Fraiman Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$425,433

$0

$425,433

$0

$425,433

 

Championship Course Maintenance Building Drainage & Washpad Improvements

 

A 2020 Capital Improvement Project, this project will improve surface and sub-surface drainage, construct a modern wash pad facility, and spot treat pavement failures at the Championship Golf Maintenance Building. This project addresses health and safety issues and prevents future water damage to this facility. A local engineering consultant completed the design and the construction contract was awarded at the June 23, 2020 Board of Trustees meeting. Construction has commenced and the project is scheduled to be completed this October. 

Cruz Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$425,433

$50,902

476,335

64,447

$411,885

 

imagIncline Park Facility Renovations 

 

This project brought substantial upgrades to Ballfield #3, located within Incline Park near the Middle School.  Construction buttoned up for the season in October last year, with punchlist items and the scoreboard installation put off until this summer. The scoreboard has been installed (photo) and this project is now substantially complete. Bring on the tournaments.

 

RaPiD Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$1,456,654

-$41,650

$1,415,004

$1,412,504

$2,500

 

The Engineering Division is also overseeing a number of projects in the construction, bidding, design and planning phases, including (but not limited to): Improvements to the Burnt Cedar swimming pools, District pavement maintenance, golf course cart path evaluations, drainage improvements at the Village Green restrooms, elevator modernization, upstairs restroom and locker room remodels at the Rec Center, installation of new catering kitchen equipment at the Chateau, revegetation monitoring at Diamond Peak culvert replacement site, replacement of the emergency fuel tank at BCWDP, and other maintenance and upgrade projects at the WRRF and BCWDP.